Due to planning and good fiscal responsibility, Deer Lofts HOA has completed over $525,000 in capital projects since 2020. These projects were completed with 100% reserve funding. No special assessments were issued for these projects.
Our philosophy is to maintain a health reserve fund over time so that all owners, including new and long term, pay into reserves for their share of maintenance, repair and enhancements. A healthy reserve fund also makes it easier for new owners to find financing.
Completed
Roof Deck floor board replacements and resealing
July 2025
Replace boards, stain, pressure wash, materials,
$5967
Reserve funded, paid cashCorrugated metal panels on front of building
Clean, paint
June 2025
$10,272
Reserve funded, paid cash
Punch button locks
Elevator room and rooftop access for HVAC (property manager has codes)
May 2025
$400 Reserve funded, paid cash
Trash room preventative maintenance
Line walls with plywood to keep walls intact and to keep rodents from entering walls.
July 2025
$900
Reserve funded, paid cash
Sewer line repair to City main
May 2023
$28,500
Reserve funded, paid cash
Parking Lot Resurfacing
December 2023
$84,680
Reserve funded, paid cash
Roof Membrane
Q3 2022
$225,000
Reserve funded, paid cash
Elevator Rehab
Q2 2020
$175,000
Reserve funded, paid cash
Planned
2025
Package locker and new mailboxes - $30-35,000 will be Reserve funded, paid cash
Out for Bids but not yet approved
Gate receiver - New receiver will be going out for bids soon. Current receiver is not consistently working. The user has be at the gate when it did work.
Replace awnings on front of building - Out for bids
2026 and beyond
Public area painting
Façade Maintenance
Deck enhancements